Bathroom Remodel: A Complete Product List.

A complete bathroom remodel involves 8 to 12 product categories depending on scope (powder room vs primary bath with separate tub and walk-in shower). This guide lists every category in the order spec decisions typically land, with links to the relevant Crateworks category for direct sourcing.

Updated May 31, 2026

The complete product list.

Vanity (cabinet + countertop + sink): the largest spec decision. Floor-mounted, wall-mounted (floating), or freestanding. Single or double sink. See bathroom vanity.

Tub: freestanding (clawfoot or modern) or alcove (built-in). Decided based on bath size and aesthetic. See bath tubs.

Shower: framed glass enclosure, frameless, walk-in, sliding, or open shower. Decided based on bath layout. See shower doors.

Toilet: standard floor-mounted, wall-hung (modern installation), or smart toilet. Specify early; affects rough-in.

Tile: floor tile, wall tile, shower tile, niche tile. Often coordinated as a family (large-format floor + smaller wall + mosaic accent in niche). See tile.

Plumbing fixtures: bathroom faucet (widespread, centerset, single-hole), shower fixtures (rain head, hand-held, body sprays), tub filler, toilet trim. See sanitary faucets.

Lighting: vanity sconces, ceiling overhead, shower light if applicable, accent or task lighting. See lighting.

Mirror: framed or frameless, single or double, with or without integrated lighting and demister.

Hardware: cabinet pulls, towel bars, robe hooks, paper holder. Coordinates with plumbing and lighting finish.

Optional: heated floor system, exhaust fan, custom storage built-ins, sauna or steam shower upgrade. See cabinets for built-in storage.


Common questions.

What is the order to spec a bathroom?
Vanity and tub or shower configuration first (the architectural pieces), then tile, then plumbing fixtures, then lighting and mirror, then hardware. Toilet specifications happen early because they affect rough-in plumbing.
Can I source all bathroom products from one supplier?
Yes through Crateworks coordinated direct sourcing. Vanity, tub, shower doors, tile, lighting, plumbing fixtures, and hardware can ship coordinated as a single project package.
How long does a bathroom remodel take?
Product specification: 4 to 6 weeks. Product delivery: 10 to 16 weeks from order. Construction: 4 to 8 weeks on site. Total project from start to finish: 18 to 30 weeks.